Silverado Canyon Road Bridge 174 pipeline project

Work to reroute a water pipeline to continue service while the County of Orange replaces Silverado Canyon Bridge 174.

Project overview

Irvine Ranch Water District contractors will be doing work to reroute a water pipeline to continue service while the County of Orange replaces Silverado Canyon Bridge 174 (55C-0174), where the existing pipeline is located.

The bridge is located on Silverado Canyon Road between the polo club and the community center.

Bridge traffic will be reduced to one lane during all phases of construction, between the hours of 7 a.m. and 5:30 p.m., Monday through Friday.

Construction updates

A temporary water line has been completed and put into service, and the County of Orange is expected to begin work on the bridge in spring of 2026.

irwd_allicons2road_closure
February through March 2025 (IRWD):

To make way for the bridge construction, IRWD contractors will install a water pipeline across Silverado Canyon Road to tie into a new main water line.

irwd_allicons2road_closure
irwd_allicons2road_closure
February through October, 2026 (County of Orange):

The County of Orange will be replacing bridge. (Contact Orange County Public Works at 714-667-8800 for information on the bridge work.)

irwd_allicons2road_closure
irwd_allicons2road_closure
November through December, 2026 (IRWD):

IRWD contractors will install a new pipeline supported by the new bridge. Remaining pipeline will be abandoned, and a surge relief vault will be demolished.

irwd_allicons2road_closure

Questions?

IRWD

For information on IRWD construction, please email info@IRWD.com  or call 949-453-5500.

County of Orange

For information on the bridge construction, please call the Orange County Public Works Department at 714-667-8800.