Sewer Siphon improvements project

IRWD contractors will be making improvements to several of the district’s sewer siphons.

Project overview

Sewer siphons divert sewage flow under, over, or around an obstacle such as a creek. Improvements at each site will vary.

Construction timing

Construction is expected to take place from April 2025 to April 2026, with each location taking about two months to complete.

Construction hours will vary by location:

irwd_allicons2construction
S1

(San Diego Creek & University) 8 a.m. to 4:30 p.m.

irwd_allicons2construction
irwd_allicons2construction
S3

(Michelson & Riparian) 7 a.m. to 3:30 p.m.

irwd_allicons2construction
irwd_allicons2construction
S5

(Jamboree & Main) 9 a.m. to 3 p.m.

irwd_allicons2construction
irwd_allicons2construction
S8

(Jeffrey & Alton) 8 a.m. to 4:30 p.m.

irwd_allicons2construction
irwd_allicons2construction
S9

(Sand Canyon & Barranca) 7:30 a.m. to 3:30 p.m. Night work near Sand Canyon Medical Center from 9 p.m. to 5:30 a.m.

irwd_allicons2construction
irwd_allicons2construction
S16

(University & Milano) 7 a.m. to 3:30 p.m.

irwd_allicons2construction
irwd_allicons2construction
S18

(Harvard & University) 9 a.m. to 3 p.m.

irwd_allicons2construction

Improvements at each site will vary but may include

Removal and replacement of concrete slabs

Installation of new composite manholes

Installation of flow control devices

Coating of concrete surfaces

Site improvements

Air vent installation

CIPP lining of siphon barrels